Core Control Solutions have designed, manufactured and integrated the engineering systems for the new Terminal T2A, T2B, MSCP 2, T2AA and Stands which include the following types of systems;
This project has been implemented over the past 24 months with the terminal scheduled to open in June 2014. This project has been challenging and rewarding, working to tight deadlines and Interfacing with a multitude of CBi’s and third party suppliers. We have designed and commissioned 12 Outstations and 52 RTU’s across the site which report back to a central SCADA system in the “STAR” centre.